Hi All,
I am looking for a different angle. Just had my defence struck out and summary judgment entered against me. Received a faulty DN from Claimant which was, in my view, short on time to remedy. So at the Claimant's Application Hearing last month my argument was based on s7 of Interpretation Act and the Claimants response to this was that the accumulative effect of s176/189 of the CCA 1974 gave a contrary intention and therefore s7 of Interpretation Act did not have any effect. DJ sided with the Claimant's barrister and therefore struck out my defence and entered the judgment in their favour.
Some of my notes from the Judgment are as follows:
The main argument is the validity of the Default Notice.
The DN was clearly produced on 25-09-09
The DN was received on or about 01-10-09
Date for compliance was 12-10-09
If the date of service was on or about 01-10-09 then there were insufficient days to remedy.
If the date of service was on 25-09-09 then there were sufficient days to remedy.
Defendant’s position was that the Interpretation Act (s7) applies to the service of a DN.
The issue in question is whether s7 applies to the CCA 1974 or whether a contrary intention appears in the CCA 1974.
s88(1)b of CCA 1974 gives that the DN must contain the remedy and a date, s88(2) says that there is a requirement for 14 days.
s176 CCA 1974 (Service of Documents) gives (1) and (2) that DN sent/delivered and (3) sent by post.
s189 CCA 1974 (Definitions) gives that ‘serve on’ means to deliver or send.
Claimant argues that these provisions make it clear that there is a contrary indication.
Claimant quotes Goode (Consumer Credit) – s76 Notice – refers to s176 of CCA 1974 and gives a meaning of ‘mode of service’.
DJ was surprised that there are no references to DN in Goode after the CCA 1974 is 36 years old.
The accumulative definition of ‘properly served’ from s176/189 gives a contrary term.
However, this is awkward due to s88(2) gives that there must be 14 clear days.
What is the date of service? s176/189 gives a contrary meaning and therefore Interpretation Act s7 does not apply and therefore DN is valid due to service is deemed to have occurred when the DN is put in the post.
I still believe that I have a sound argument/defence. I therefore believe an Appeal could be a way forward. However, I need the evidence to aid my Appeal. With the clock ticking I have approximately 9 days to apply for the Appeal.
Any help would be much appreciated,
Thanks, in advance.
TMTR
I am looking for a different angle. Just had my defence struck out and summary judgment entered against me. Received a faulty DN from Claimant which was, in my view, short on time to remedy. So at the Claimant's Application Hearing last month my argument was based on s7 of Interpretation Act and the Claimants response to this was that the accumulative effect of s176/189 of the CCA 1974 gave a contrary intention and therefore s7 of Interpretation Act did not have any effect. DJ sided with the Claimant's barrister and therefore struck out my defence and entered the judgment in their favour.
Some of my notes from the Judgment are as follows:
The main argument is the validity of the Default Notice.
The DN was clearly produced on 25-09-09
The DN was received on or about 01-10-09
Date for compliance was 12-10-09
If the date of service was on or about 01-10-09 then there were insufficient days to remedy.
If the date of service was on 25-09-09 then there were sufficient days to remedy.
Defendant’s position was that the Interpretation Act (s7) applies to the service of a DN.
The issue in question is whether s7 applies to the CCA 1974 or whether a contrary intention appears in the CCA 1974.
s88(1)b of CCA 1974 gives that the DN must contain the remedy and a date, s88(2) says that there is a requirement for 14 days.
s176 CCA 1974 (Service of Documents) gives (1) and (2) that DN sent/delivered and (3) sent by post.
s189 CCA 1974 (Definitions) gives that ‘serve on’ means to deliver or send.
Claimant argues that these provisions make it clear that there is a contrary indication.
Claimant quotes Goode (Consumer Credit) – s76 Notice – refers to s176 of CCA 1974 and gives a meaning of ‘mode of service’.
DJ was surprised that there are no references to DN in Goode after the CCA 1974 is 36 years old.
The accumulative definition of ‘properly served’ from s176/189 gives a contrary term.
However, this is awkward due to s88(2) gives that there must be 14 clear days.
What is the date of service? s176/189 gives a contrary meaning and therefore Interpretation Act s7 does not apply and therefore DN is valid due to service is deemed to have occurred when the DN is put in the post.
I still believe that I have a sound argument/defence. I therefore believe an Appeal could be a way forward. However, I need the evidence to aid my Appeal. With the clock ticking I have approximately 9 days to apply for the Appeal.
Any help would be much appreciated,
Thanks, in advance.
TMTR
Comment