• Welcome to the LegalBeagles Consumer and Legal Forum.
    Please Register to get the most out of the forum. Registration is free and only needs a username and email address.
    REGISTER
    Please do not post your full name, reference numbers or any identifiable details on the forum.

Problem with builder

Collapse
Loading...
X
  • Filter
  • Time
  • Show
Clear All
new posts

  • #16
    Re: Problem with builder

    Originally posted by Ripped-Off View Post
    If you terminate the contract and you were wrong to do so then the builder can sue you for not allowing him to perform his contract for you.

    I did not terminate the contract, he did. He walked out, but is claiming we mutually agreed to end the contract.


    In your text you state that he walked off the job because you refused to pay him for:
    • a lintel that the building inspector says should be changed
    • plastering that is not completed and
    • for brick work that will need to be knocked down.
    • Correct, plus some other brickwork he claims he did on the gable ends, but there is nothing there except thin air. There is nothing in writing about this so-called extra brickwork, and I can assure you he put everything in writing, especially where it involved extra money. I think of this as the 'imaginary' brickwork! Finally, he wants money for the roof timbers, but this bears no relation to the shape of the roof on the drawings, and the inspector says it's not properly supported. I suspect this will have to come down, but I'm not sure at this stage. It is very knotty, cheap-looking wood which I suspect is pine, and we had a no pine agreement in the contract as I hate it.


    Now, the common law of set-off allows you to offset any costs that you have incurred against any money that you owe. However, a set-off can never exceed the amount owing, otherwise it becomes a counterclaim.

    He claims I owe him £2k. I'm not sure yet how much I think he owes me, but I think it will be in the region of £10k. I need to get written quotes to fix the work and complete the job as per the drawings and building control satisfaction. Are you saying I can only claim a maximum of £2k as that is all he is claiming? This doesn't make sense.


    Furthermore, the law of abatement allows you to reduce payments for incomplete work, defective work or to correct an overpayment. The saying is...one cannot owe something that is not due.

    Good, makes sense.

    What should have happened is that you should have paid him for the work that he has done, less any amounts that you are entitled to retain through set-off and abatement.

    Easy to say in theory, but once he had started he then demanded money in advance. He told me work was complete,, and I did not know the inspector would condemn it. Lesson learned, I will never take a builder's word again without confirmation from building control.

    However, these figures should be calculable. If that means that the payment due is zero, so be it, as long as you have calculated the amount of the payment. To simply say 'I am not paying you' without providing any substantiation could be viewed as a breach of contract.

    I listed the defects, and told him I would have to get quotes. I also explained why I do not believe I owe him the sums he is claiming for me. Our payment schedule stated payment on completion of each stage. The roof is not completed, so no payment is due until completion, for example. Also, he has made up the extra brickwork as there is nothing in the contract or any subsequent emails about this. The lintel has not been agreed by building control, so it would be foolish for me to pay for this until it is changed to the type specified by the council.


    If, however, full substantiation has been provided then the builder has a remedy of suing you for the money that he believes is owing, he cannot simply walk off site. To do so would in itself amount to a breach of contract.

    And I wonder if this is why he is now claiming we terminated the contract by mutual agreement? I did not agree to terminate, but I could not force him to continue. He said he would sue me for the money, but has made no efforts to do this, or send a letter before action. He said he had a solicitor working for him, but I'm not sure I believe this. The reason he gave at the time for walking off is that he no longer trusts me as I called building control in. However, he had acted recklessly in knocking through a supporting wall without checking for adequate support first, when the drawings and his contract both stated he would check first. Then there was a panic while he grabbed a lintel and put it in, but the inspector won't accept it. He gets very emotional, and behaved like a spoilt child, bleating and whining about how good his work is, but the council is wrong, the drawings are wrong and also I'm wrong! Think of a two-year-old having a tantrum and you'll get the picture.

    Supposing that you have not breached the contract from your side, then it must follow that he has breached it from his. That gives you the opportunity to terminate the contract, seek damages and any losses incurred. One aspect of your loss will be the extra cost, if any, of employing someone to complete the works.

    I've written him two letters before action, but have not yet given him a figure as I don't have quotes yet. I suspect, logically, I will need to send him a third
    letter once I have figures to give him a chance to know what the damages will be? He might reconsider re-doing the work himself once he has figures?

    You don't have to have incurred the cost beforehand. As long as you can quantify the damages/loss that you will suffer as a result the of non performance, the Court may allow your claim.

    Why do you say 'may' rather than 'will' (assuming I win in court, of course). I've been watching a few Judge Judy's, and sometimes she pays quotations, and sometimes she says the plaintiff will have to come back once they have paid the bill and incurred the damage. Maybe different rules for different USA states? What's the rule in the UK?

    For example, Contract Value = £50k, paid = £30k, cost to complete = £30k, loss = £10k. This is based on you mitigating your losses to the full extent. You can't simply bring in a world class builder and expect your builder to bear the difference in cost.

    Yes, it will be to complete as per the drawing specification. For example, the drawing states an LG steel lintel, and the builder has used a cheaper concrete lintel which will have to be changed.

    You must prove that what you have paid to date is equal to what the work is worth.

    I've paid more because some of the work has been condemned, and some is not completed.

    The building inspector's report should suffice for defects, after all, even if you employed a building surveyor and he disagreed with the building inspector, you are still going to either have to pay to have the building inspector's decision reviewed or pay to have the work corrected to the satisfaction of the building inspector.

    OK, I have the email from the inspector.

    However, the building surveyor's report should concur with the building inspector's decision and that will be good evidence, as well as a witness statement from the architect.

    So do I need to get a separate surveyor's report as well? I moved house last year, and I know these cost over £1k.


    Finally. as for mutual termination, you say that you have numerous records requesting that builder return to complete. I would say that is a good start to show that neither had discharged the other from their respective obligations. It is for the builder to prove mutual discharge, not you. He will no doubt rely on this as a defence to a claim.
    Thanks, a very useful reply, lots for me to think about.

    The main thing I will need to look into is how vital it is to have a separate surveyor's report.

    What about the witness statement from the architect? Is there a particular form this should take, are there guidelines, what should it include? I have emails from the architect, but not a witness statement. Should I pay him for this?

    Comment


    • #17
      Re: Problem with builder

      can I ask a few questions
      How much money has not been paid to the builder to date and what was the quoted price?

      Comment


      • #18
        Re: Problem with builder

        Why do you say 'may' rather than 'will' (assuming I win in court, of course).
        I've no idea how much the opinion of a QC will be, but if you want certainty then you should seek one out. Without knowing the full story behind your claim 'may' is the best I can offer.

        He claims I owe him £2k. I'm not sure yet how much I think he owes me, but I think it will be in the region of £10k. I need to get written quotes to fix the work and complete the job as per the drawings and building control satisfaction. Are you saying I can only claim a maximum of £2k as that is all he is claiming? This doesn't make sense.
        Yes, that is exactly what I am saying. However, if you go to Court as the Claimant you can claim as much as you like providing you can persuade the court. If you go as the defendant then your defence cannot exceed the amount he is claiming from you otherwise you must make a separate counterclaim. When you counter claim there are effectively two trials dealt with at the same time. His claim against you and your claim (known as a counterclaim) against him. Say he owes you £10k and you owe him £2k and he takes you to court, you will have to raise your £10k as a counterclaim. Alternatively, if you take him to court he can raise the £2k as a set-off against the £10k he owes you, providing of course that both he and you can persuade the court.

        I've been watching a few Judge Judy's, and sometimes she pays quotations, and sometimes she says the plaintiff will have to come back once they have paid the bill and incurred the damage. Maybe different rules for different USA states? What's the rule in the UK?
        I've never watched it myself, though if it's anything like 'Judge Rinder' I would take it all with a large pinch of salt.

        If I were you, I would read section s49 - s58 of the Consumer Rights Act 2015 (applies to consumer contracts entered into after October 2015), your claims and remedies will flow from this. Draw up a letter referring to the relevant sections of the Act, advise that you intend to instruct a building surveyor and recover the cost ( I think £1k is a bit steep), enclose quotes from the builders (but not their names, he may know them!) and give him one last chance.

        Comment


        • #19
          Re: Problem with builder

          Originally posted by Ripped-Off View Post



          Yes, that is exactly what I am saying. However, if you go to Court as the Claimant you can claim as much as you like providing you can persuade the court. If you go as the defendant then your defence cannot exceed the amount he is claiming from you otherwise you must make a separate counterclaim. When you counter claim there are effectively two trials dealt with at the same time. His claim against you and your claim (known as a counterclaim) against him. Say he owes you £10k and you owe him £2k and he takes you to court, you will have to raise your £10k as a counterclaim. Alternatively, if you take him to court he can raise the £2k as a set-off against the £10k he owes you, providing of course that both he and you can persuade the court.

          So If I claim £10 from him and he claims £2k from me, would that still be a small claim (£10k - £2k = £8k), or would the numbers be added together to make £12k, hence taking it over the small claims limit?

          If I were you, I would read section s49 - s58 of the Consumer Rights Act 2015 (applies to consumer contracts entered into after October 2015), your claims and remedies will flow from this. Draw up a letter referring to the relevant sections of the Act, advise that you intend to instruct a building surveyor and recover the cost ( I think £1k is a bit steep), enclose quotes from the builders (but not their names, he may know them!) and give him one last chance.
          Thanks, I'm looking at this. What does 'without prejudice' mean? For example, 'without prejudice to subsection (1).

          This is the stuff I've been going through with Citizens' Advice, asking him to return and do the work again, but he won't. Having spoken to another builder who knows him, I now think he is out of his depth and has no idea how to fix the problems, so it's probably better for me if he doesn't return.

          I don't have figures proving exactly what I need to claim as a price reduction, and this is what I need to do next. So do I need a surveyor before I get more quotes? Looking through the surveyor websites, is it a 'defect report' that I need? A full building survey around here costs £1k+ as I had one last year when I bought the current house.

          He also did not give me a cooling off notice - can I bring this in to my claim?

          Comment


          • #20
            Re: Problem with builder

            So If I claim £10 from him and he claims £2k from me, would that still be a small claim (£10k - £2k = £8k), or would the numbers be added together to make £12k, hence taking it over the small claims limit?
            Yes, I believe so. If both amounts are less than £10k that should suit the Small Claims Court.

            What does 'without prejudice' mean? For example, 'without prejudice to subsection (1).
            "Without prejudice to" is used in a clause where there is to be no priority given over another clause. It tells the reader that the clause in which the expression appears does not affect the clause to which it refers.

            I don't have figures proving exactly what I need to claim as a price reduction, and this is what I need to do next. So do I need a surveyor before I get more quotes?
            I would say so. The surveyor will list out the items he considers are incomplete or defective. You can then raise the contents of the survey with the builders if they fail to notice something, or quote for something that the surveyor considers satisfactory. If the only problems are the brickwork, plastering and a lintol, then I cannot conceive how a survey could be more than a few hundred quid. Use the RICS website when selecting a surveyor, ring them, explain the problems and they will provide a quote for exactly what you need.

            He also did not give me a cooling off notice - can I bring this in to my claim?
            There is no harm in trying. However, without knowing the details it is difficult to say. If you do raise that argument the builder might be able to argue that you allowed him to start, you could have stopped him at anytime afterwards before costs became excessive and therefore you have waived your right to a cooling off period.

            Comment


            • #21
              Re: Problem with builder

              Originally posted by Ripped-Off View Post




              There is no harm in trying. However, without knowing the details it is difficult to say. If you do raise that argument the builder might be able to argue that you allowed him to start, you could have stopped him at anytime afterwards before costs became excessive and therefore you have waived your right to a cooling off period.

              Thanks for your replies.

              Regarding cooling off, I could not have stopped him at any time, as I and a contract with him and would have been in breach of contract if I tried to stop him after the contract was signed.

              He began work less than 14 days after the contract was signed in my home, and the 2013 legislation seems to be saying he should have (a) given me a cooling off notice, and (b) got my written consent to begin work within the 14 days. He did neither.

              Comment


              • #22
                Re: Problem with builder

                Originally posted by Ripped-Off View Post



                I would say so. The surveyor will list out the items he considers are incomplete or defective. You can then raise the contents of the survey with the builders if they fail to notice something, or quote for something that the surveyor considers satisfactory. If the only problems are the brickwork, plastering and a lintol, then I cannot conceive how a survey could be more than a few hundred quid. Use the RICS website when selecting a surveyor, ring them, explain the problems and they will provide a quote for exactly what you need.

                I have a surveyor who did the survey when I bought the house last year.

                So, do I need to:

                1. find out how much the defect survey will cost.

                2. send another letter before action to the builder telling him i am having the defect survey done and how much it will cost

                3. send him the bill after it's done.

                Getting the order of things right seems to be important and I want to make sure I don't slip up.

                Comment


                • #23
                  Re: Problem with builder

                  Regarding cooling off, I could not have stopped him at any time, as I and a contract with him and would have been in breach of contract if I tried to stop him after the contract was signed.
                  he should have (a) given me a cooling off notice, and (b) got my written consent to begin work within the 14 days. He did neither.
                  If the contract has 14 days to become active then you could have stopped him within those 14 days without breaching the contract, couldn't you?

                  It makes no difference if you include more than one argument relating to the same point, in fact it should be encouraged. If you fail on one of your arguments then you may well succeed on an alternative argument. The only drawback is that if the judge considers that you are being vexatious or your alternative arguments are frivolous, then you could end up with a larger share of the costs when the judge apportions them.

                  Getting the order of things right seems to be important and I want to make sure I don't slip up.
                  You could have the survey done now, before you draft your letter. This will mean a greater initial outlay or wasted expense if he comes to his senses. On the other hand if you don't have the survey done, your letter before action may be diminished in that it lacks all the expert evidence that you may want to rely on in court. You can, however, still have the survey done before you file your claim with the court. Just send him a copy of the report and await a response before filing the claim. In any event, any reports or evidence that you rely on may require the writer of that report to give a witness statement or even to attend court to give evidence. That could mean the building inspector, the architect, the building surveyor and yourself.

                  My own preference would be to have the survey done now. I would also advise you to have a read of the Civil Procedure Rules which govern the procedure for court action. Go to https://www.justice.gov.uk/courts/pr...es/civil/rules and read parts 4, 6, 7, 12, 16, 22, 24, 27, 32, 33, 35, 41 & 44. Each part has a corresponding practice directions to offer guidance.

                  Also review the Pre-Action Protocol For Construction & Engineering Disputes at http://www.justice.gov.uk/courts/pro...tocol/prot_ced. This will tell you the procedure that you must follow when drafting your letter.

                  Comment


                  • #24
                    Re: Problem with builder

                    Before spending money try if possible to find out if this guy has the ability to pay you if you win,
                    I asked before how much of the original quote has been paid ?

                    Comment


                    • #25
                      Re: Problem with builder

                      I believe the OP said he was a sole trader not a limited company.

                      Unless he disposes of all of his personal assets then I shouldn't think it would be too much of a problem suing him personally. The OP may even be able to obtain a Charging Order, but I think you have to get a judgement in your favour first.

                      Comment


                      • #26
                        Re: Problem with builder

                        All the assets might be in wifes name no guarantee he has anything im only suggesting try to find out first

                        Comment


                        • #27
                          Re: Problem with builder

                          Originally posted by wales01man View Post
                          Before spending money try if possible to find out if this guy has the ability to pay you if you win,
                          I asked before how much of the original quote has been paid ?
                          he drives a £20k car. I'm not sure it matters how much I've paid him as I will only be claiming the cost to remedy the work, and I don't know this yet.

                          Comment


                          • #28
                            Re: Problem with builder

                            I drive a 17k car nut I don't own it means nothing go ahead and take him to court looks like you have a very good chance of winning getting the money may be harder.

                            Comment


                            • #29
                              Re: Problem with builder

                              Originally posted by Ripped-Off View Post
                              If the contract has 14 days to become active then you could have stopped him within those 14 days without breaching the contract, couldn't you?

                              No, because he did not give me a cooling off notice (which is a criminal offence) and I did not realise that he should have given me a cooling off notice until Citizens' Advice brought this to my attention later. If I had had a cooling off notice I would have cooled off, because his whole attitude changed after I signed the contract.

                              It makes no difference if you include more than one argument relating to the same point, in fact it should be encouraged. If you fail on one of your arguments then you may well succeed on an alternative argument. The only drawback is that if the judge considers that you are being vexatious or your alternative arguments are frivolous, then you could end up with a larger share of the costs when the judge apportions them.

                              ​If it goes to small claims there will be no costs awarded either way. I'm beginning to sound as though I know what I'm talking about!



                              You could have the survey done now, before you draft your letter. This will mean a greater initial outlay or wasted expense if he comes to his senses. On the other hand if you don't have the survey done, your letter before action may be diminished in that it lacks all the expert evidence that you may want to rely on in court. You can, however, still have the survey done before you file your claim with the court. Just send him a copy of the report and await a response before filing the claim. In any event, any reports or evidence that you rely on may require the writer of that report to give a witness statement or even to attend court to give evidence. That could mean the building inspector, the architect, the building surveyor and yourself.

                              ​Some good points here, I think I need to get an appointment with a solicitor who has done this before to work out what I need to do and the order.

                              My own preference would be to have the survey done now. I would also advise you to have a read of the Civil Procedure Rules which govern the procedure for court action. Go to https://www.justice.gov.uk/courts/pr...es/civil/rules and read parts 4, 6, 7, 12, 16, 22, 24, 27, 32, 33, 35, 41 & 44. Each part has a corresponding practice directions to offer guidance.

                              Thanks for the links. My head is so full of rules I need to clear it before I look at any more!

                              Also review the Pre-Action Protocol For Construction & Engineering Disputes at http://www.justice.gov.uk/courts/pro...tocol/prot_ced. This will tell you the procedure that you must follow when drafting your letter.

                              Thanks, Ripped-off. I'll take a look at these.

                              Comment


                              • #30
                                Re: Problem with builder

                                Originally posted by wales01man View Post
                                I drive a 17k car nut I don't own it means nothing go ahead and take him to court looks like you have a very good chance of winning getting the money may be harder.
                                He's a good 20 years younger than I am, so even if it is paid back monthly I think I could get most of it back. He is separated from his daughter's mother, so I doubt anything will be in her name. He apparently has a current partner who is male, so possibly assets could be in his name, but I can be patient and get paid monthly. He is a very good plasterer by all accounts, so my aim is to stop him trying to be a general builder and go back to plastering, as I think he will earn more this way.. I'm thinking of going to the local press as I suspect they like stories about cowboy builders, to prevent any other locals employing him to do their building work. This might help him to re-consider returning to plastering.

                                Comment

                                View our Terms and Conditions

                                LegalBeagles Group uses cookies to enhance your browsing experience and to create a secure and effective website. By using this website, you are consenting to such use.To find out more and learn how to manage cookies please read our Cookie and Privacy Policy.

                                If you would like to opt in, or out, of receiving news and marketing from LegalBeagles Group Ltd you can amend your settings at any time here.


                                If you would like to cancel your registration please Contact Us. We will delete your user details on request, however, any previously posted user content will remain on the site with your username removed and 'Guest' inserted.
                                Working...
                                X