So in July last year (2020) we accepted a quote for a builder to come and take down a conservatory and replace it with a proper extension, take down some internal walls and fit a new kitchen. The builder took down and removed the old conservatory, and starting digging the footings for the foundations. Unfortunately, the existing house foundations turned out to be about twice as deep as we thought, which meant getting a digger in to finish the excavation and liaising with the structural engineer to update plans, which all took time. (In actual fact, the builder kept saying for 2 weeks he couldn't get a digger operator to come and have a look at the site, we got one out the same afternoon and he was ready to start in 2 days time. Plus, the builder never established the depth of the existing foundations either, we had to do this ourselves).
By November, the structural engineer had updated the plans and we were ready to get started again, but by that point it was clear the builder wasn't interested in doing the work. He refused to answer calls, voicemails, emails or messages on his business Facebook page. In January he finally responded and basically said (reluctantly) he can continue with the work if we wanted, but has pulled 2 big projects forward and so doesn't know when we would be able to start, and then says he understands if we want to look for alternatives to complete the work. So now he's basically abandoned the project.
Unfortunately, we paid just under £7k (20% of the total project) a few days before all the issues came about. We asked for a breakdown of the work and individual payments. He has overcharged by £500 for the labour, is witholding the RSJs, and cancelled an order for windows and doors without out instruction and has kept that money. We have emailed him seeking a compromise basically asking him for a refund for the above items. If he doesn't respond or if he refuses to pay, I'll look to other means to recover the money. Question is, from a legal perspective, what could I actually claim?
Could I go for a full refund as he didn't complete the whole project, even though he did do the conservatory removal work, or can in only claim for the individual items as mentioned above?
Thanks in advance!
By November, the structural engineer had updated the plans and we were ready to get started again, but by that point it was clear the builder wasn't interested in doing the work. He refused to answer calls, voicemails, emails or messages on his business Facebook page. In January he finally responded and basically said (reluctantly) he can continue with the work if we wanted, but has pulled 2 big projects forward and so doesn't know when we would be able to start, and then says he understands if we want to look for alternatives to complete the work. So now he's basically abandoned the project.
Unfortunately, we paid just under £7k (20% of the total project) a few days before all the issues came about. We asked for a breakdown of the work and individual payments. He has overcharged by £500 for the labour, is witholding the RSJs, and cancelled an order for windows and doors without out instruction and has kept that money. We have emailed him seeking a compromise basically asking him for a refund for the above items. If he doesn't respond or if he refuses to pay, I'll look to other means to recover the money. Question is, from a legal perspective, what could I actually claim?
Could I go for a full refund as he didn't complete the whole project, even though he did do the conservatory removal work, or can in only claim for the individual items as mentioned above?
Thanks in advance!
Comment