I am a first time poster and first time litigant, so my apologies for this outpouring...
I purchased a listed property from a BtL landlord in August 2014. I needed to complete within 3 weeks for personal reasons. All seemed in order until my own research identified planning and building control issues with the property that had not been disclosed in the SPIF or by my solicitor's searches and additional enquiries. I attributed a general lack of compliance/paperwork to the death of her son in the property - advised by a neighbour - around the same time as these works took place.
I requested an indemnity policy or £30k price reduction for three specific potential liabilities (no completion certificate for some works carried out in 2010, no planning permission for a balcony that had been installed, and a claim of water ingress to neighbouring property that was apparently still 'currently being investigated but all indications suggest not to blame". The vendor agreed to a £15k price reduction and we completed the transaction.
Within weeks I discovered that the vendor had already spent £2k on unsuccessful repairs on the drain system to overcome the neighbour's water ingress issue. A month before she put the property on the market the managing agent had advised her that the specialist contractor recommended the next step to sorting the problem was to rip out the kitchen and dig out the concrete ground floor.
I discovered widespread woodworm, wet rot and structural issues - all well covered up and not identified by my limited specialist survey pre-contract that was arranged to address evident rising dampness on the ground floor (failed DPC).
I then discovered the boiler was illegally installed, having been supplied by the vendor's ex-husband and installed by a mate of the appointed builder who did the works four years earlier. Reported the matter to Gas Safe, who inspected and declared it unsafe
I then discovered (failed) DPC and woodworm treatments (without rectification works) were arranged by the vendor in 2009 and not disclosed. Nor were the associated 30 year guarantees. I would not have bought the property if I had known that the vendor had installed a DPC less than five years earlier and it had already failed (turns out there are groundwater flooding issues at the property, also not disclosed).
I looked at the SPIF more closely and worked out that 20% of her responses were false.
I raised allegations of false statements, non-disclosure and illegal works with the vendor's (conveyancing) solicitor at the end of April 2015. Response "Information given in good faith, did not try to mislead you and strongly refutes your allegations". I advised that I intended to seek redress through litigation. The firm's litigation solicitor then asked for evidence, which I provided, along with a Schedule of Works and estimates, quotations and provisional sums totalling over £65,000 to carry out unknown, post-contract remedial works.
A letter of response finally arrived in late July two weeks after the 28 day period initially agreed for a response and after a threat of Court proceedings. The defendant's solicitor said she had psychologically distanced herself from the property, admitted inaccurate (but not dishonest) information in the SPIF but no misrepresentation as inaccurate information given by their client did not induce you (me) to exchange contracts. Should have had a full structural survey on such an old property. And anyway, caveat emptor applies. My response pointed out the degree of inaccuracy in the SPIF amounted to dishonesty, many assertions made in this letter relating to information the vendor said she provided to my solicitor pre-contract were simply false and that caveat emptor does not apply where deliberate dishonesty has occurred.
Nothing more heard so I then made an offer of formal mediation. In August I received the response that his client and his firm still did not understand my claim. So I represented all the information and documents already sent in strict Pre-Action Protocol format. This resulted in the vendor apparently seeking advice from Counsel.
Three weeks later I have receive a demand for my conveyancing file, given I had apparently foregone legal privilege by referring to correspondence between myself and my solicitor at some point, and the threat of a pre-action disclosure application (at my expense) if not forthcoming. The offer of a possible informal meeting instead of formal mediation was made, but only after my solicitor had handed over my conveyancing file and all correspondence between us.
I have now reached Day 150 after more than 13 weeks of clearly deliberate delays by the defendant's solicitor. I have threatened Court proceedings, only to receive the same retort each time that such an action would be premature and inappropriate.
I sought preliminary legal advice from two firms (one the firm that did my conveyancing) at the outset, but would like to avoid significant further legal costs if I possibly can. A Google search shows that her litigation solicitor prides himself for his tactics of delay, stamina and nerve! He clearly doesn't take me or my claim seriously and has been regularly rude and unprofessional in the way he addresses me in correspondence between us.
Any comments on the validity of my claim, and suggestions on how I should now proceed would be much appreciated.
I purchased a listed property from a BtL landlord in August 2014. I needed to complete within 3 weeks for personal reasons. All seemed in order until my own research identified planning and building control issues with the property that had not been disclosed in the SPIF or by my solicitor's searches and additional enquiries. I attributed a general lack of compliance/paperwork to the death of her son in the property - advised by a neighbour - around the same time as these works took place.
I requested an indemnity policy or £30k price reduction for three specific potential liabilities (no completion certificate for some works carried out in 2010, no planning permission for a balcony that had been installed, and a claim of water ingress to neighbouring property that was apparently still 'currently being investigated but all indications suggest not to blame". The vendor agreed to a £15k price reduction and we completed the transaction.
Within weeks I discovered that the vendor had already spent £2k on unsuccessful repairs on the drain system to overcome the neighbour's water ingress issue. A month before she put the property on the market the managing agent had advised her that the specialist contractor recommended the next step to sorting the problem was to rip out the kitchen and dig out the concrete ground floor.
I discovered widespread woodworm, wet rot and structural issues - all well covered up and not identified by my limited specialist survey pre-contract that was arranged to address evident rising dampness on the ground floor (failed DPC).
I then discovered the boiler was illegally installed, having been supplied by the vendor's ex-husband and installed by a mate of the appointed builder who did the works four years earlier. Reported the matter to Gas Safe, who inspected and declared it unsafe
I then discovered (failed) DPC and woodworm treatments (without rectification works) were arranged by the vendor in 2009 and not disclosed. Nor were the associated 30 year guarantees. I would not have bought the property if I had known that the vendor had installed a DPC less than five years earlier and it had already failed (turns out there are groundwater flooding issues at the property, also not disclosed).
I looked at the SPIF more closely and worked out that 20% of her responses were false.
I raised allegations of false statements, non-disclosure and illegal works with the vendor's (conveyancing) solicitor at the end of April 2015. Response "Information given in good faith, did not try to mislead you and strongly refutes your allegations". I advised that I intended to seek redress through litigation. The firm's litigation solicitor then asked for evidence, which I provided, along with a Schedule of Works and estimates, quotations and provisional sums totalling over £65,000 to carry out unknown, post-contract remedial works.
A letter of response finally arrived in late July two weeks after the 28 day period initially agreed for a response and after a threat of Court proceedings. The defendant's solicitor said she had psychologically distanced herself from the property, admitted inaccurate (but not dishonest) information in the SPIF but no misrepresentation as inaccurate information given by their client did not induce you (me) to exchange contracts. Should have had a full structural survey on such an old property. And anyway, caveat emptor applies. My response pointed out the degree of inaccuracy in the SPIF amounted to dishonesty, many assertions made in this letter relating to information the vendor said she provided to my solicitor pre-contract were simply false and that caveat emptor does not apply where deliberate dishonesty has occurred.
Nothing more heard so I then made an offer of formal mediation. In August I received the response that his client and his firm still did not understand my claim. So I represented all the information and documents already sent in strict Pre-Action Protocol format. This resulted in the vendor apparently seeking advice from Counsel.
Three weeks later I have receive a demand for my conveyancing file, given I had apparently foregone legal privilege by referring to correspondence between myself and my solicitor at some point, and the threat of a pre-action disclosure application (at my expense) if not forthcoming. The offer of a possible informal meeting instead of formal mediation was made, but only after my solicitor had handed over my conveyancing file and all correspondence between us.
I have now reached Day 150 after more than 13 weeks of clearly deliberate delays by the defendant's solicitor. I have threatened Court proceedings, only to receive the same retort each time that such an action would be premature and inappropriate.
I sought preliminary legal advice from two firms (one the firm that did my conveyancing) at the outset, but would like to avoid significant further legal costs if I possibly can. A Google search shows that her litigation solicitor prides himself for his tactics of delay, stamina and nerve! He clearly doesn't take me or my claim seriously and has been regularly rude and unprofessional in the way he addresses me in correspondence between us.
Any comments on the validity of my claim, and suggestions on how I should now proceed would be much appreciated.
Comment