I have a design and build contract with a limited company.
The contract was for them to build me a house by 20/12/2012 that passed building regulations.
The builder has made so many mistakes that the knock on effect is that they have not had the money to complete the work and are now nearly a year overdue.
We are up to date with our agreed instalments.
Luckily the build quality is good although we have an issue with the render and a problem with the drains but nothing we cant fix.
If they complete the work then we still have an instalment of £23k plus £3k defect retention to pay.
We have however had to pay for some of the work and materials that they should have done because they couldn't afford it.
The builder says the project has already overspent by £55k which I can quite believe due to their mistakes.
I estimate that we have spent £5-8k on work he should have done and that there is £12-15k work left to do (He says about £7k left to do)
It is clear he cannot finish the work.
He came to us on Friday and advised us he would become insolvent in 2 weeks if he can't get some money in to rescue the business.
In reality we have a nice house for the money we have paid but it is not complete.
The builder wants to end the contract and has asked us to pay him £15k to do this.
He says if we dont then he will become bankrupt and that the insolvency administrators are very clever and will claim back the £55k overspend from us using a law that I have heard of.
Any advice please
The contract was for them to build me a house by 20/12/2012 that passed building regulations.
The builder has made so many mistakes that the knock on effect is that they have not had the money to complete the work and are now nearly a year overdue.
We are up to date with our agreed instalments.
Luckily the build quality is good although we have an issue with the render and a problem with the drains but nothing we cant fix.
If they complete the work then we still have an instalment of £23k plus £3k defect retention to pay.
We have however had to pay for some of the work and materials that they should have done because they couldn't afford it.
The builder says the project has already overspent by £55k which I can quite believe due to their mistakes.
I estimate that we have spent £5-8k on work he should have done and that there is £12-15k work left to do (He says about £7k left to do)
It is clear he cannot finish the work.
He came to us on Friday and advised us he would become insolvent in 2 weeks if he can't get some money in to rescue the business.
In reality we have a nice house for the money we have paid but it is not complete.
The builder wants to end the contract and has asked us to pay him £15k to do this.
He says if we dont then he will become bankrupt and that the insolvency administrators are very clever and will claim back the £55k overspend from us using a law that I have heard of.
Any advice please
Comment