Hello thank you for allowing me to join.
I have a couple of questions regarding a contract between myself and a builder which was drawn up by an Architect (using a RIBA Domestic Building Contract 2018). I am trying to resolve some issues with mediation.
1. The completion date was specified as a fixed date. The work over-ran by several months. One section says it is the Contractor's Obligation to finish by the completion date. There is a section about liquidated damages that mentions I can claim the amount mentioned in a box in section L. The box in section L is blank so I assume I cannot claim any money?
2. Other than liquidated damages there does not seem to be much I can do regarding the over run. Does it matter that the builder breached the contract? The delay has cost me money as the property was to be rented out as a holiday let.
3. Under Contract Price there are two tick boxes: "Calculated in accordance with the pricing documents listed under item D" and "Specified Below" with the latter being checked and an amount listed beneath it. There is mention of a Schedule of Works in item D and the estimate in that document is higher than the one "Specified Below" but should I regard the one "Specified Below" as being the price to work to?
4. The architect has been listing "Additional Items" in a spreadsheet and adding them to the bill. For example: I additionally asked for some new windows. In total should I pay the "Specified Below" Contract Price + Additional Items + VAT and nothing more to the builder?
5. In the contract definitions it says this: "Contract price: The amount that the Client shall pay to the Contractor for carrying out and completing the Works, calculated in accordance with clause 7 of the Contract. Note: The Contract price may increase (or decrease) as a result of instructions given by the Architect/Contract Administrator" - does this really mean the Architect can just change the Contract Price however he wishes? I am more inclined to think this means the price can change when the architect requests a change to the original specification etc?
6. The architect has sent me 4 Interim Payment Certificates and each has a section called "Amount of any adjustments required in accordance with the Contract" and all are blank. Is this where any change to the Contract Price mentioned above should be listed or is that for something else?
Sorry for the long post and thank you very much in advance for any replies.
I have a couple of questions regarding a contract between myself and a builder which was drawn up by an Architect (using a RIBA Domestic Building Contract 2018). I am trying to resolve some issues with mediation.
1. The completion date was specified as a fixed date. The work over-ran by several months. One section says it is the Contractor's Obligation to finish by the completion date. There is a section about liquidated damages that mentions I can claim the amount mentioned in a box in section L. The box in section L is blank so I assume I cannot claim any money?
2. Other than liquidated damages there does not seem to be much I can do regarding the over run. Does it matter that the builder breached the contract? The delay has cost me money as the property was to be rented out as a holiday let.
3. Under Contract Price there are two tick boxes: "Calculated in accordance with the pricing documents listed under item D" and "Specified Below" with the latter being checked and an amount listed beneath it. There is mention of a Schedule of Works in item D and the estimate in that document is higher than the one "Specified Below" but should I regard the one "Specified Below" as being the price to work to?
4. The architect has been listing "Additional Items" in a spreadsheet and adding them to the bill. For example: I additionally asked for some new windows. In total should I pay the "Specified Below" Contract Price + Additional Items + VAT and nothing more to the builder?
5. In the contract definitions it says this: "Contract price: The amount that the Client shall pay to the Contractor for carrying out and completing the Works, calculated in accordance with clause 7 of the Contract. Note: The Contract price may increase (or decrease) as a result of instructions given by the Architect/Contract Administrator" - does this really mean the Architect can just change the Contract Price however he wishes? I am more inclined to think this means the price can change when the architect requests a change to the original specification etc?
6. The architect has sent me 4 Interim Payment Certificates and each has a section called "Amount of any adjustments required in accordance with the Contract" and all are blank. Is this where any change to the Contract Price mentioned above should be listed or is that for something else?
Sorry for the long post and thank you very much in advance for any replies.
Comment