Hallo
I would be grateful for any general advice about the following.
I have had an on going subsidence claim with a major insurance company since 1999. After several years in which the company would not accept that there was subsidence at my property, remedial work was commenced in summer of 2007. I complained that the work (pilling) had not solved the problem and had left my property in a worse condition than before it had been carried out. The Financial Ombudsman Service has been less than helpful and eventually told me to "prove it". It has taken a few years to obtain an Expert Witness report which identifies that the Insurance company, their agents and the Ombudsman were all negligent.
The Report is adequate in that it identifies the negligence and goes into substantial detail about how and why the negligence occurred. What gives me cause for concern is that the report stops short of discussing what the insurance company and the builder they instructed to remedy defects did, although the Expert witness knows about this and I provided photographic evidence.
The original claim was that a garage/utility room extension was separating from the main house. The Expert Witness identified the cause as being that a drain under the garage had collapsed leaving water running to ground since 1999 or earlier, the insurance company and their agents failed to do a drains test and water continued to leak under the garage and probably house foundations. He has identified that various tests now need to be done to establish what damage has been caused and then to rectify various issues that he has identified.
What concerns me is that although he now says the garage is out-of-square and requires to be rebuilt from ground level upwards along with that section of the roof being rebuilt and mentions some fault with roof voids between the garage floor and the underlying utility room, he has failed to disclose in his report that the garage was previously rebuilt from ground level upwards, the section of the roof was not rebuilt and is consequently twisted, the insurance company and their builder intended to do a cosmetic repair by raising ground across the entire front of my house and gardens by 4 inches, raised the garage floor by 4 inches and took out the damp course that was part of the garage reconstruction and there is some visible defect in the underlying utility room that is causing the artex ceiling to peel off all along the interior wall below that part of the garage from which the damp course was removed.
I hope I have explained why I am concerned but the fact that the Expert Witness knows all this, has evidence (provided by me) and has omitted it from his report has made me suspect that as well as the negligence he identified, what the insurance company and their latest builder have done is in fact reckless and not merely negligent. The builder acted on the instruction of the person who was at the time the insurance company's Subsidence/Technical Claims manager (with appropriate qualifications) and I have only just found out the time of my original insurance claim in 1999 and up until December 2002 he was Regional Engineer Manager for the firm of Loss Adjusters appointed by the insurance company and who failed to identify the reported subsidence.
Obviously this is a total mess and I cannot begin to think how to get out of it but what I am thinking now is that the Insurance company's then Subsidence/Technical Claims manager (who was the Regional Engineer Manager for the Loss Adjusters who are identified in the Expert Witness report as being negligent for failing to do a drains test) has been criminal in instructing the builder to do what I can prove he did. The Insurance person has substantial qualifications and an extremely high profile CV. There is no way he would not have been aware of the consequences of his actions.
Anyway, to cut a long story short, should I be reporting this to the police?
Thanks for any advice or opinion you may be able to provide.
I would be grateful for any general advice about the following.
I have had an on going subsidence claim with a major insurance company since 1999. After several years in which the company would not accept that there was subsidence at my property, remedial work was commenced in summer of 2007. I complained that the work (pilling) had not solved the problem and had left my property in a worse condition than before it had been carried out. The Financial Ombudsman Service has been less than helpful and eventually told me to "prove it". It has taken a few years to obtain an Expert Witness report which identifies that the Insurance company, their agents and the Ombudsman were all negligent.
The Report is adequate in that it identifies the negligence and goes into substantial detail about how and why the negligence occurred. What gives me cause for concern is that the report stops short of discussing what the insurance company and the builder they instructed to remedy defects did, although the Expert witness knows about this and I provided photographic evidence.
The original claim was that a garage/utility room extension was separating from the main house. The Expert Witness identified the cause as being that a drain under the garage had collapsed leaving water running to ground since 1999 or earlier, the insurance company and their agents failed to do a drains test and water continued to leak under the garage and probably house foundations. He has identified that various tests now need to be done to establish what damage has been caused and then to rectify various issues that he has identified.
What concerns me is that although he now says the garage is out-of-square and requires to be rebuilt from ground level upwards along with that section of the roof being rebuilt and mentions some fault with roof voids between the garage floor and the underlying utility room, he has failed to disclose in his report that the garage was previously rebuilt from ground level upwards, the section of the roof was not rebuilt and is consequently twisted, the insurance company and their builder intended to do a cosmetic repair by raising ground across the entire front of my house and gardens by 4 inches, raised the garage floor by 4 inches and took out the damp course that was part of the garage reconstruction and there is some visible defect in the underlying utility room that is causing the artex ceiling to peel off all along the interior wall below that part of the garage from which the damp course was removed.
I hope I have explained why I am concerned but the fact that the Expert Witness knows all this, has evidence (provided by me) and has omitted it from his report has made me suspect that as well as the negligence he identified, what the insurance company and their latest builder have done is in fact reckless and not merely negligent. The builder acted on the instruction of the person who was at the time the insurance company's Subsidence/Technical Claims manager (with appropriate qualifications) and I have only just found out the time of my original insurance claim in 1999 and up until December 2002 he was Regional Engineer Manager for the firm of Loss Adjusters appointed by the insurance company and who failed to identify the reported subsidence.
Obviously this is a total mess and I cannot begin to think how to get out of it but what I am thinking now is that the Insurance company's then Subsidence/Technical Claims manager (who was the Regional Engineer Manager for the Loss Adjusters who are identified in the Expert Witness report as being negligent for failing to do a drains test) has been criminal in instructing the builder to do what I can prove he did. The Insurance person has substantial qualifications and an extremely high profile CV. There is no way he would not have been aware of the consequences of his actions.
Anyway, to cut a long story short, should I be reporting this to the police?
Thanks for any advice or opinion you may be able to provide.
Comment