Hi,
I am new to the forum and started a small claims (as an individual) against a glazing company for breach of contract.
The case has been rather prolonged for various reasons, I will try to summarise but apologise in advance for the long post,
The company was contracted to supply and install bifolds in my new kitchen extension last year. Their surveyor came out to survey the opening, order details etc.
The screed and floor were not down yet and we communicated very clearly the system track must line up flush to the projected finished floor, to prevent tripping, protruding parts etc. The surveyor requested express terms in the contract, after liaising with the site contractor the glazing company emailed a contract with accurate millimetre heights.
The surveyor called me over the phone (call recorded) to confirm everything as agreed. I paid a deposit and confirmed the contract between myself and the company.
Long story short, the installation went through and signed off by the glazing company. The building work moved forward. All balance paid in good faith that the company had performed the contract as expected by a reasonably competent professional. The tiles went down at later date in line with the ground floors and it was brought to my attention the track was protruding over the floor by a margin of centimetres.
I am not a surveyor and in this instance had to triple check measurements before appointing responsibility.
I notified the glazing company and right from the start they argued everything was done right. To keep this short, I made a timeline below,
The damages include part removal of render and plaster/plasterboard outside and inside the building respectively, decorations etc. There is risk of damage to tiles and kitchen furniture. The cost is in the range of few thousand pounds assuming the system is reused and refitted.
The company argue they do not have to cover making good damages because this was new built and incomplete at the time of fitting.
According to their rationale it was someone else's responsibility to evaluate the errors in their works against the contract. I simply put it they have to bring me in the position I would have reasonably been under the contract execution.
Due to the complexity of the case, precision agreed and continuous dispute from the other party, I decided to appoint the independent expert witness pre-action. I would have difficulty supporting my own measurements to a judge. However I do understand they need to approve the report during DQ stage, so I may not be able to claim that cost back.
I am a little overwhelmed about performing at a hearing, how to prepare/present evidence and ensure I follow the CPR rules. Especially because they are a mid-scale company and will potentially afford a solicitor to represent them, argue details or use case law.
Any help on how to prepare before the defence would be most welcome.
I am new to the forum and started a small claims (as an individual) against a glazing company for breach of contract.
The case has been rather prolonged for various reasons, I will try to summarise but apologise in advance for the long post,
The company was contracted to supply and install bifolds in my new kitchen extension last year. Their surveyor came out to survey the opening, order details etc.
The screed and floor were not down yet and we communicated very clearly the system track must line up flush to the projected finished floor, to prevent tripping, protruding parts etc. The surveyor requested express terms in the contract, after liaising with the site contractor the glazing company emailed a contract with accurate millimetre heights.
The surveyor called me over the phone (call recorded) to confirm everything as agreed. I paid a deposit and confirmed the contract between myself and the company.
Long story short, the installation went through and signed off by the glazing company. The building work moved forward. All balance paid in good faith that the company had performed the contract as expected by a reasonably competent professional. The tiles went down at later date in line with the ground floors and it was brought to my attention the track was protruding over the floor by a margin of centimetres.
I am not a surveyor and in this instance had to triple check measurements before appointing responsibility.
I notified the glazing company and right from the start they argued everything was done right. To keep this short, I made a timeline below,
- Jan 2018 - company notified of issue and invited on site / they denied responsibility outright / requested system drawings
- Feb 2018 - company became unresponsive / no site visit / case submitted with all evidence to mediation scheme they are a member of
- April 2018 - long trail of wasted communications / company refused the error but proposed "goodwill offer" under terms to reposition system / "terms" were that all making good damages to the building should be covered by client.
- May 2018 - One of the directors accepted to visit site 4 months late to measure / a witness was present. They arrived premeditated to blame the issue to the floor / they took measurements and photos pretty much proving doors are in the wrong position. They simply repeated "conditional goodwill-only" offer.
- The offer was reject as unacceptable, too many risks and costs while the other party was at fault not admitting the breach. The company somehow assumed they have the right to return on site for works after 8 months while disputing any responsibility.
- May 2018 - I sent a final settlement offer equal to the refitting cost they disclosed, much lower to the remedial costs. The reason was to receive part compensation and appoint a competent installer to undertake the full remedial works. They rejected the offer in a very rude email claiming I was after making money.
- June 2018 - Mediation scheme offers arbitration but the company says "case is closed and we do not want to hear again".
- June 2018 -Evidence, remedial quotes and expert witness estimates are collected / Served Final Notice with steps and timeline asked other party to disclose evidence.
- July 2018 - Notice expires without reply / I extended notice by 7 days on email, company responds they accept none of my views or positions, 3rd party survey costs etc and stand by goodwill offer / I instruct independent Expert Witness pre-action due to the precision of the error and complexity
- Sep 2018 - Report conclusion is that doors were designed shorter and fitted higher than contract
- Oct 2018 - Claim, Particulars of Claim and annexed report are all served to defendant
The damages include part removal of render and plaster/plasterboard outside and inside the building respectively, decorations etc. There is risk of damage to tiles and kitchen furniture. The cost is in the range of few thousand pounds assuming the system is reused and refitted.
The company argue they do not have to cover making good damages because this was new built and incomplete at the time of fitting.
According to their rationale it was someone else's responsibility to evaluate the errors in their works against the contract. I simply put it they have to bring me in the position I would have reasonably been under the contract execution.
Due to the complexity of the case, precision agreed and continuous dispute from the other party, I decided to appoint the independent expert witness pre-action. I would have difficulty supporting my own measurements to a judge. However I do understand they need to approve the report during DQ stage, so I may not be able to claim that cost back.
I am a little overwhelmed about performing at a hearing, how to prepare/present evidence and ensure I follow the CPR rules. Especially because they are a mid-scale company and will potentially afford a solicitor to represent them, argue details or use case law.
Any help on how to prepare before the defence would be most welcome.
Comment