Re: Cowboy builders taking me to court with a no win no fee lawyer after 16 months.
I will try and deal with some of your comments. I can't do them all otherwise the post will be far too long. This is not legal advice but just my opinion....
I will make the following assumptions.
Were these terms incorporated into the contract and did you fulfil your part of the bargain?
Incidentally, 5 x £14,590.35 = £72,951.75, add the initial £14,590.35 and the total is only £87,542.10. What happens to the remainder?
Was there a retention amount specified in the contract?
Was there a rectification period provided where the builder is required to return to remedy defects before the retention is released to him?
Did the architect issue payment notices in accordance with clause 4.3 which states 'interim payments to the Contractor shall be the dates occurring at intervals of 4 weeks calculated from the Date for Commencement of the Works. Not later than 5 days after each due date the Architect/Contract Administrator shall issue an interim certificate for a sum equal to the percentage stated in the Contract Particulars of what he considers to be the total value as at the due date '?
Note the contractor's obligations at clause 2.1......The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents,..
You are technically in breach of the contract here. You did not give an instruction to omit works, and worse still you carried them out yourself. The builder is entitled to recover lost profit on the omitted work but not the value of the work itself, see AMEC Building Ltd v Cadmus Investments Co Ltd (1997).
The render is a matter of fact and is easily proven. Were the door thresholds a requirement of the contract or an afterthought?
Patent defects should be corrected before the works are certified as complete. Without a completion certificate the builder cannot get his final payment nor the retention. Clause 4.3.1 refers to 'work properly executed' as a condition for payment.
Did you or the architect issue a Practical Completion certificate? Once issued the defects rectification period begins. The builder must return to correct any notified defects within a reasonable time. Where there is no rectification period you are at liberty to employ others to correct any notified defects and recover those costs from the builder. However, you should give notice to the builder of your intention - see Pearce & High Ltd v Baxter and another - [1999].
These are called Provisional sums and covered by clause 3.7. Unless the builder is given an instruction to spend the money then he is not entitled to payment at all. In effect he has done work that you have not asked for. However, you knew what he was doing and allowed that to happen so the law of estoppel would prevent you from relying on the clause. Nevertheless, the law of abatement allows you to reduce the payment to him and he is put to strict proof to show that the door (materials and labour) are worth the amount claimed.
Tell me you haven't paid it!!
An example of your Pre Action protocol mediation/negotiation obligations. Were records kept? Are there any sound witnesses?
Boom!!! a potential repudiatory breach of contract. He has breached his contractual obligation to repair defects. Is this in writing from the builder who signed the contract with you!! I doubt whether, after so long, you can accept repudiation, but you can claim damages.
Your builder is claiming from you but you appear to have a strong case to counter-claim or set-off for the cost of rectifying the defective work. That is the basis of your defence. Unfortunately, the pair of you have not helped by failing to administer the contract correctly.
In addition to the above, what was the architect's role in all of this? Did you pay him to administer the contract? He may well have owed you a duty of care which he has breached.
I will try and deal with some of your comments. I can't do them all otherwise the post will be far too long. This is not legal advice but just my opinion....
I will make the following assumptions.
- You have a copy of the signed agreement.
- The architect was noted in the contract as the administrator.
- The contract was JCT 2011 Minor Works.
- You are the employer.
The build was for £92149.60 and a build time of 10 weeks. Payment scale of initial payment of 14,590.35 followed by 5 bi monthly payments of 14,590.35
Incidentally, 5 x £14,590.35 = £72,951.75, add the initial £14,590.35 and the total is only £87,542.10. What happens to the remainder?
Was there a retention amount specified in the contract?
Was there a rectification period provided where the builder is required to return to remedy defects before the retention is released to him?
Did the architect issue payment notices in accordance with clause 4.3 which states 'interim payments to the Contractor shall be the dates occurring at intervals of 4 weeks calculated from the Date for Commencement of the Works. Not later than 5 days after each due date the Architect/Contract Administrator shall issue an interim certificate for a sum equal to the percentage stated in the Contract Particulars of what he considers to be the total value as at the due date '?
By 21st December and nearly 6 weeks in very little progress had been made
quotation we had included a kitchen, and front and garage doors with a budget for each. I finally measured up and ordered a kitchen myself
Render had massive cracks in, roof leaked, 3 different height door thresholds which were all too high for my disabled mum.
Patent defects should be corrected before the works are certified as complete. Without a completion certificate the builder cannot get his final payment nor the retention. Clause 4.3.1 refers to 'work properly executed' as a condition for payment.
Did you or the architect issue a Practical Completion certificate? Once issued the defects rectification period begins. The builder must return to correct any notified defects within a reasonable time. Where there is no rectification period you are at liberty to employ others to correct any notified defects and recover those costs from the builder. However, you should give notice to the builder of your intention - see Pearce & High Ltd v Baxter and another - [1999].
A budget of 1000.00 was for a new front door and they put on a 200.00
There was the final payment which included a retention for snagging left to pay.
We had numerous onsite meetings with them going through all the defects and agreed but they never came back
one of the builders telling us to get others to finish as relations had broken down
Your builder is claiming from you but you appear to have a strong case to counter-claim or set-off for the cost of rectifying the defective work. That is the basis of your defence. Unfortunately, the pair of you have not helped by failing to administer the contract correctly.
In addition to the above, what was the architect's role in all of this? Did you pay him to administer the contract? He may well have owed you a duty of care which he has breached.
Comment