Hi,
I hope someone is able to help as we are a small company and really don't know what to do.
We have recently (in the past 7 months) started working as a sub-contractor for a much larger company.
We originally came into contact with this larger company with the intention of carrying out a 7 month project with them which was due to start June 2023, as the project is so large it would require our whole work force to be on site for the duration. We were promised the job would start so we ceased finding our own projects. The job how ever was pushed back time and time again so luckily the main contractor provided us with smaller fill in jobs.
We have now seen what this main contractor is like to work for they bring the moral of the team down and payments are awful they are finding any excuse not to pay our invoices and the relationship is not a good one.
The large project is due to start on Monday and we would love to pull out but do not know where we stand. We have a contract that we signed at the beginning of July and in the contract it mentions a completion date of the 28th Dec, obviously due to the 6 month delay in the start date this end date will not stand.
Is there any way we can pull out of this job due to the delay in the start date and the contract no longer being accurate?
Any help would be greatly appreciated.
Thank you .
I hope someone is able to help as we are a small company and really don't know what to do.
We have recently (in the past 7 months) started working as a sub-contractor for a much larger company.
We originally came into contact with this larger company with the intention of carrying out a 7 month project with them which was due to start June 2023, as the project is so large it would require our whole work force to be on site for the duration. We were promised the job would start so we ceased finding our own projects. The job how ever was pushed back time and time again so luckily the main contractor provided us with smaller fill in jobs.
We have now seen what this main contractor is like to work for they bring the moral of the team down and payments are awful they are finding any excuse not to pay our invoices and the relationship is not a good one.
The large project is due to start on Monday and we would love to pull out but do not know where we stand. We have a contract that we signed at the beginning of July and in the contract it mentions a completion date of the 28th Dec, obviously due to the 6 month delay in the start date this end date will not stand.
Is there any way we can pull out of this job due to the delay in the start date and the contract no longer being accurate?
Any help would be greatly appreciated.
Thank you .
Comment