• Welcome to the LegalBeagles Consumer and Legal Forum.
    Please Register to get the most out of the forum. Registration is free and only needs a username and email address.
    REGISTER
    Please do not post your full name, reference numbers or any identifiable details on the forum.

Confused legal advice on when the Limitation clock started ticking

Collapse
Loading...
X
  • Filter
  • Time
  • Show
Clear All
new posts

  • Confused legal advice on when the Limitation clock started ticking

    Hello hoping someone can check my sanity!


    A money claim for approx approx £7500 was lodged against me on 3rd Feb 2026
    I've drafted and submitted a defence. The primary defence is that the claim is statute barred.
    Mediation call happened - no budging on either side so this is going to court.
    I've called the legal advice team on my home insurance.
    Both they and the mediator advised that the case is not time barred as the invoice the Claimant wants to claim for was dated 3rd Feb 2020.
    I pointed out 2 things.

    1. My understanding is that the 6 years for litigation doesn't start from the date of invoice. The limitation clock starts ticking from the day after the last day services are performed. This is a good summary I found that explains this.;

    https://www.hailshamchambers.com/res...e-start-to-run

    2. The invoice dated 3rd Feb 2020 was a rehash of an earlier invoice sent on 9th Jan 2020 for the exact same services provided. No services were performed between the first and second invoice. No agreement or committment to pay was ever given by me to the first or second invoice.

    Particulars of Claim:
    The Claimant, a heating engineer, gave the Defendant (me) a fixed price quote for a new heating system in August 2019.
    The Defendant paid the deposit and purchased the materials as per the payment schedule set out by the Claimant.
    The works started but then started taking longer than all the estimates.
    It appeared to the Defandant that maybe the Claimant wasn't as experienced as he'd represented.
    The Claimant left the site for the last time with everything unfinished on 8th Jan 2020. Nothing connected and nothing turned on as per the quote.
    The Claimant decided to unilaterally charge an extra amount to the Defendant to cover the "extra" time spent.
    The Defendant protested and emailed that this was a surprise, that there was no verbal agreement to vary and no new services were requested. Everything should be completed as per the original quote.
    The Claimant did not agree and the relationship broke down.
    The Claimant then sent an email with a rehashed invoice on 3rd Feb 2020 explaining that he wants to again vary the contract unilaterally and the work done up until 8th Jan 2020 should be invoiced even higher by charging me hourly instead of daily.
    I never agreed to this invoice either.

    When does the limitation clock start ticking?
    All the case law and articles say the Courts vigorously resist allowing the date of invoice being the cause of action.
    This was a "simple" contract without any terms varying the right to payment arising the moment the work finished.
    There was no agreement reached. My only replies to him after that date are to say that I disagree.
    The second invoice the Claimant is relying on is a rehash of the first - for the exact same work. Are people allowed to keep invoicing to extend the 6 year window?

    The paralegal level people I'm being given to are interpreting all of that inversely. They say the date of the second invoice is the cause of action.

    Am I wrong??
    Tags: None

  • #2
    Were there any contract terms, particularly specifying when payment would be due?

    For example, if there was a term providing for payment within 30 days of invoice, your argument would fail in respect of the 9 January invoice.
    Lawyer (solicitor) - retired from practice, now supervising solicitor in a university law clinic. I do not advise by private message.

    Guides and handbooks for Litigants in Person - :

    https://legalbeagles.info/forums/for...60#post1701560

    Comment


    • #3
      My interpretation of paragraphs 12 and 14 under "Contract for work or services " in the article provided is that time starts to run when the work is finished regardless of when the work is invoiced.
      Contractual provisions must be clear.

      Did you receive a certificate for the work carried out? If not you should have got another gas safe engineer to inspect and certify the work.

      Comment


      • #4
        I researched that such as I can. I found that all the cases over the last 100-something years don't recognise payment window terms as altering the accrual of the right to payment and from that the cause of action. The most recent case was in the UK appeal court. Here's an article that explains that:

        https://www.nortonrosefulbright.com/...n-work-is-done

        Consulting Concepts International Inc. v Consumer Protection Association (Saudi Arabia), the Court of Appeal ruled that the limitation period begins when work is completed, not when a contractual invoice payment window (e.g., 90 days) expires. Such payment terms are merely procedural bars and do not delay the accrual of the cause of action.

        There was no express contractual terms at all in my case. Just a "simple" contract of Offer, Acceptance, Consideration in the form of the quote, the emails and the deposit and payments I made. So there's no terms that could constitute a variance of the right to payment.

        The work wasn't finished. It was left unfinished. Nothing connected or working at all. Just some panels mounted on the roof. The invoice being claimed for was for a number of days labour - despite the quote specifying a complete job including a line item for "Labour, installation and commissioning" of the system. There was no other agreement on a day rate or other method of calculating payment. There was a line in the quote that said "If you request changes to the specification that involves additional cost, or there are exceptional circumstances that we could not reasonably have foreseen that mean additional works are required, we will provide you with a revised quote". No revised quote was given at any time.

        The quote was approx £4k for a complete system. His 9th Jan 2020 invoice first wanted to charge an extra approx £3.5k out of the blue without any discussion. I said that's not on. He refused to budge and threatened not to return. I said I can't work with him unilaterally feeling that he can depart from our agreement. He doubled down and on 3rd Feb 2020 sent a new invoice for the exact same dates of work done, this time increasing the invoice to £4.8k. He's relying on this second invoice to be the start date for Limitation.

        Every single person I speak to seems to default to thinking the invoice date starts limitation but the case law and articles seem to suggest otherwise. Is it really that misunderstood? My imposter syndrome makes me feel I can't be the only one seeing this.
        Last edited by Rkeeper; Yesterday, 10:18:AM.

        Comment


        • #5
          The way I have always looked at it is that if payment terms are 30 days, then if payment is not made within that time, the cause of action accrues on the date of the breach of contract - the 30th day.

          Thankfully, none of my clients chose to wait 6 years to sue, so none of my cases needed to be examined in that kind of detail.

          Try this argument: if payment terms are 30 days, would you really start a court claim on day 15, absent a clear express statement of refusal to pay?
          Lawyer (solicitor) - retired from practice, now supervising solicitor in a university law clinic. I do not advise by private message.

          Guides and handbooks for Litigants in Person - :

          https://legalbeagles.info/forums/for...60#post1701560

          Comment


          • #6
            I'd totally see where you're coming from if this was a breach of contract defence or a common sense interpretation. However, it's neither. I'm going to court on a limitation defence primarily, and I'm looking up the court's most common interpretation of the statute. How the court usually treats this is the crux for me.

            Plenty of cases appear to have tried to persuade the court that the limitation clock should be paused / altered to accommodate their situation. Payment due terms, negotiations, conflicting terms preventing payment etc etc.

            https://www.hilldickinson.com/our-vi...-stop-ticking/

            The court has refused to stop the clock ticking in every case I've found. I started trying to look up construction cases like mine but then widened the net. I haven't found a case where they've accepted anything other than very explicit terms in the contract to defer the right to payment itself away from the day after services were last provided.

            I'm worried because legally trained people are giving me seemingly incorrect advice. My nightmare is that the judge makes the same mistake!

            Comment


            • #7
              I quote this from the link in post #6:

              The 120-day period for payment for the cargoes expired at different dates between November 2013 and March 2014, depending on the bill of lading date for the cargo. The Court held that Sahara's losses stemmed from breaches by Sonara in failing to make payment by the 120th day after the date of the bills of lading. There was no contractual time bar but, for the purposes of the time bar under the Act, time began running at the end of each of those 120-day periods and expired six years later.
              As I said earlier, are there any written terms (e.g. with the initial quotation that you accepted) which specify when payment is due?

              Has the Claimant responded to your limitation argument? If so, what has it said?
              Lawyer (solicitor) - retired from practice, now supervising solicitor in a university law clinic. I do not advise by private message.

              Guides and handbooks for Litigants in Person - :

              https://legalbeagles.info/forums/for...60#post1701560

              Comment


              • #8
                Hi - sorry I didn't reply more clearly. I've just had another look.

                The quotes say:
                40 % On the order
                30 % One week before the job starts
                30% Blance on completion

                I had paid the first 2 which were not invoiced - I just paid on the basis of the quote.

                I didn't pay the last part as the job wasn't completed.

                There are no written payment terms on the only 2 invoices I got. There are no written payment terms in any other communications we had.

                Comment


                • #9
                  I suggest an additional alternative defence that this "balance" is not due, the job not having been completed.

                  What about my other question - has the claimant responded to the limitation defence?
                  Lawyer (solicitor) - retired from practice, now supervising solicitor in a university law clinic. I do not advise by private message.

                  Guides and handbooks for Litigants in Person - :

                  https://legalbeagles.info/forums/for...60#post1701560

                  Comment


                  • #10
                    There was barely anything in the case the claimant put forward. Literally a couple of sentences.
                    There's been no dialogue with the claimant directly after I submitted a defence.
                    During mediation I made my limitation case to the mediator which though they felt honour bound to point out to me that it was incorrect, they dutifully passed on to the claimant.
                    The mediator then came back to me to say the claimant was sure the claim was in time based on the 3rd Feb 2020 invoice.
                    So clearly they haven't looked into it.

                    I have submitted the full breach of contract particulars within that defence too.

                    Can I write to the court and ask that this matter be struck out on the basis of limitation?

                    Or will I have to defend myself to make the particulars of limitation clear before they'd establish that it's really out of time?

                    Comment


                    • #11
                      You will have to persuade the court that the case is time barred. The court may direct a hearing specifically on that question, or it may deal with the point as part of the overall trial of the claim.
                      Lawyer (solicitor) - retired from practice, now supervising solicitor in a university law clinic. I do not advise by private message.

                      Guides and handbooks for Litigants in Person - :

                      https://legalbeagles.info/forums/for...60#post1701560

                      Comment

                      View our Terms and Conditions

                      LegalBeagles Group uses cookies to enhance your browsing experience and to create a secure and effective website. By using this website, you are consenting to such use.To find out more and learn how to manage cookies please read our Cookie and Privacy Policy.

                      If you would like to opt in, or out, of receiving news and marketing from LegalBeagles Group Ltd you can amend your settings at any time here.


                      If you would like to cancel your registration please Contact Us. We will delete your user details on request, however, any previously posted user content will remain on the site with your username removed and 'Guest' inserted.
                      Working...
                      X