Dear all,
I need urgent advice regarding my rights for compensation. I am a subcontractor and was awarded a purchase order (PO) 15 months ago for a project that kept getting delayed. The job was scheduled to start on 27.01. Before that, on 07.01, I was informed that asbestos training was required. I was assured that updated project details would be sent to my email, but the company mistakenly sent them to another contractor instead.
I only became aware of this when I followed up, but by then, the company had already appointed another subcontractor and issued me a “non-compliance” cancellation—despite the fact that I have all valid certifications, including for my team.
The company informed me of this late on Friday, just before I was due to start on Monday. This sudden decision has left me in a difficult position, forcing me to lay off my team, as we had allocated time for this project until mid-March.
Given that:
The PO was binding.
The delay was due to their miscommunication and not my fault.
The project was not even ready to start on Monday.
I have worked with this company for nearly 10 years without issue.
Do I have grounds to claim compensation for lost earnings, negligence, or any other legal recourse? I feel this decision was unfair and based on their internal mistakes rather than any actual non-compliance on my part.
I would appreciate your guidance on how to proceed.
Thank you in advance on any suggestions


Comment