Good evening All
I am hoping to get some specific clarification for a legal matter and would appreciate some replies for which i thank you in advance!
I am the claimant in a small claims case relating to a construction case. There are a couple of specific points that are key to the case.
Firstly - during the build process, the defendant knowingly prevented us from being able to complete the works. To clarify, we were building a unit with a kitchen but the defendant had agreed to hire a plumber to do the pipework - the plumber did not arrive on site at all during the entire time we were there - so the knock on effect was that the kitchen could not be finished. There are several other similar things all relating to the same thing. Therefore we were prevented from completing. We left site asking the defendant to let us know once the plumber & other trades had done their work and then we would come back to finish - the defendant didnt contact us.
We left it for a couple of weeks and then tried to contact the defendant. He would not pick up the phone or respond to any correspondence for several weeks.
Eventually, after 4 weeks, he sent a very aggressive email detailing mostly that he wasnt paying because we hadnt finished. Obviously we were aware we hadn't finished but were totally prepared to go back.
He suggested that he could finish the work as it would be quicker so we agreed (as this was easier) and deducted some money from the bill - we asked him to confirm he was happy with this arrangement but again he didnt reply. More importantly he still didnt pay.
After many weeks and us going through the correct pre-action protocol, we issued a claim for the outstanding bill. The defendant had still not replied to anything we sent.
Finally at the deadline for replying to the court action, the defendant put in a defence and counterclaim which was completely unbelievable!
His defence was mostly the fact we hadn't finished......
BUT more aggravating was the counterclaim - which consisted of a whole range of other items that he is claiming were wrong - none of which he has ever told us about. He has made a whole list of things which we believe to be invented, but further to this, he goes onto say he has already got other contractors to fix them! So we have been prevented from completing the work in the first place and then we have been told there's a load of other things wrong but they've already been fixed by others without us being told anything.....
In light of all of the above, we have completed an N244 requesting that the defence is struck out for being unfair and unreasonable on many levels - and i would like to understand where you feel we stand with this - its giving me sleepless nights!
I am hoping to get some specific clarification for a legal matter and would appreciate some replies for which i thank you in advance!
I am the claimant in a small claims case relating to a construction case. There are a couple of specific points that are key to the case.
Firstly - during the build process, the defendant knowingly prevented us from being able to complete the works. To clarify, we were building a unit with a kitchen but the defendant had agreed to hire a plumber to do the pipework - the plumber did not arrive on site at all during the entire time we were there - so the knock on effect was that the kitchen could not be finished. There are several other similar things all relating to the same thing. Therefore we were prevented from completing. We left site asking the defendant to let us know once the plumber & other trades had done their work and then we would come back to finish - the defendant didnt contact us.
We left it for a couple of weeks and then tried to contact the defendant. He would not pick up the phone or respond to any correspondence for several weeks.
Eventually, after 4 weeks, he sent a very aggressive email detailing mostly that he wasnt paying because we hadnt finished. Obviously we were aware we hadn't finished but were totally prepared to go back.
He suggested that he could finish the work as it would be quicker so we agreed (as this was easier) and deducted some money from the bill - we asked him to confirm he was happy with this arrangement but again he didnt reply. More importantly he still didnt pay.
After many weeks and us going through the correct pre-action protocol, we issued a claim for the outstanding bill. The defendant had still not replied to anything we sent.
Finally at the deadline for replying to the court action, the defendant put in a defence and counterclaim which was completely unbelievable!
His defence was mostly the fact we hadn't finished......
BUT more aggravating was the counterclaim - which consisted of a whole range of other items that he is claiming were wrong - none of which he has ever told us about. He has made a whole list of things which we believe to be invented, but further to this, he goes onto say he has already got other contractors to fix them! So we have been prevented from completing the work in the first place and then we have been told there's a load of other things wrong but they've already been fixed by others without us being told anything.....
In light of all of the above, we have completed an N244 requesting that the defence is struck out for being unfair and unreasonable on many levels - and i would like to understand where you feel we stand with this - its giving me sleepless nights!



Comment